1. The steel structure workshop project leader or the project installation contractor shall be the person in charge of the safe construction and shall be fully responsible for the safe construction on site.
2, steel structure site safety administrator for the site safety construction full-time personnel, responsible for safety construction supervision, inspection.
3, strengthen the safety of construction publicity, in the steel structure construction site prominent location hanging slogans, warning signs, to remind the construction personnel.
4, the personnel entering the construction site must wear safety helmet.
5, construction machinery, machinery and tools daily routine inspection before use, especially steel wire rope, safety belt should also be a weekly one-time inspection, to ensure good.
6, the installation process should take into account the site machinery, equipment, completed steel structure engineering safety protection. When wind speed is 10m/s, sometimes lifting work should be stopped, and when wind speed reaches 15m/s, all work must be stopped.
7. Wear gloves when installing and handling components and plates.
8. When hoisting, the wire rope should be replaced immediately if there is broken strand, broken wire rope and entanglement.
9, special jobs need to hold valid certificate.
10. At the end of a day's work, the installation of the building should be supported correctly to avoid accidents.
11, always wear protective goggles when drilling.
12, do a good job of the site safety protection measures, according to the provisions of the scaffolding and check qualified, can be used.
13, in the installation of wall panels, the operation platform of each layer of mobile scaffolding should be fixed firmly, and do anti-skid measures, pull the protective rope, buckle the safety belt.
14, mobile scaffold and wall have more than two pull contacts, and set up two throw brace on the outside. The throw brace should be fixed on a solid ground with bearing capacity.
15, before moving to clear the obstacles on the road ahead, fill potholes, compaction road can move forward
16, in the implementation of each task, should be steel structure installation workers repeatedly explain safety matters.